Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Dec 2022 Pipe laying and HTC Connection work in progress Areacode AE
05 Dec 2022 Pipe laying and HTC Connection work in progress Areacode AE
28 Nov 2022 Pipe laying in progress. About 1900 m of 90 mm , 120 m of each 75 mm and 63 mm PVC laid. Areacode AE
24 Nov 2022 Pipe laying in progress. About 1900 m of 90 mm , 120 m of each 75 mm and 63 mm PVC laid. Areacode AE
14 Nov 2022 Pipe laying work in progress Areacode AE
07 Nov 2022 Pipe laying work in progress Areacode AE
04 Nov 2022 work order issued on 17.08.2022, Agreement executed on 06.09.2022 Malappuram PH Dn EE