- Sub:- JJM Providing WSS to Areekode Panc...
Sub:- JJM Providing WSS to Areekode Panchayath - Laying distribution Network, Changing of Damaged Clarifier bridge ,Fitting new gear box and out let pipe line for Alum Lime tank at treatment plant-reg-
Project |
Sub:- JJM Providing WSS to Areekode Panchayath - Laying distribution Network, Changing of Damaged Clarifier bridge ,Fitting new gear box and out let pipe line for Alum Lime tank at treatment plant-reg- |
Project Code |
MLPJJM022212567 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Laying distribution line : 63 PVC - 2500mtr, 75PVC -2000mtr,90 PVC-2000mtr,110 PVC - 1500mtr,140PVC -500mtr, 50 GI - 1700mtr
Changing of damaged clarifire bridge, Centre bush to new thrust bearing set in WTP,Treatment plant - Fitting new gear box and out let pipe line,Providing FHTCs - 200Nos |
Status |
On-going |
District |
Malappuram |
Executing Office |
Malappuram PH Dn |
AS Amount (Rs) |
20000000
|
AS Number |
GO(Rt) No. 134/2022/WRD |
TS Amount (Rs) |
16900000 |
TS Number |
Reg .No. 10167/2022-2023 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
200 FHTCs |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM Providing WSS to Areekode Panchayath - Laying distribution network ,Changing of Damaged Clarifier bridge ,Fitting new gear box and out let pipe line for Alum Lime tank at Treatment plant. |
Areecode PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Jun 2024 |
FHTC -88 nos Completed, Pipe line work in progress |
Areacode AE |
|
24 Jun 2024 |
FHTC -88 nos Completed, Pipe line work in progress |
Areacode AE |
|
20 Jun 2024 |
FHTC -88 nos Completed, Pipe line work in progress. |
Areacode AE |
|
14 Jun 2024 |
FHTC -88 nos Completed, Pipe line work in progress. |
Areacode AE |
|
30 May 2024 |
FHTC -88 nos Completed, Pipe line work in progress. |
Areacode AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
23/10/2022 |
Scheduled date of Completion of the Project |
22 Apr 2023 |
Expected date of Completion |
22/04/2023 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
14 Jul 2022 |