Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2023 | Pipe laying is in process. | Areacode AE | |
14 Feb 2023 | Pipe laying is in process. | Areacode AE | |
02 Feb 2023 | Pipe laying is in process. | Areacode AE | |
27 Jan 2023 | Pipe laying is in process. | Areacode AE | |
18 Jan 2023 | 1954 m of 90 mm PVC, 521 m of 75 mm PVC and 790 m of 63 mm PVC had laid. Out of 150 FHTC, 28 HTC had given. Road cutting (1.8 km) issue is pending and due to which FHTC is not increasing at a faster rate. | Areacode AE | |
05 Jan 2023 | 1954 m of 90 mm PVC, 521 m of 75 mm PVC and 790 m of 63 mm PVC had laid. Out of 150 FHTC, 28 HTC had given. Road cutting (1.8 km) issue is pending and due to which FHTC is not increasing at a faster rate. | Areacode AE | |
29 Dec 2022 | 1954 m of 90 mm PVC, 521 m of 75 mm PVC and 790 m of 63 mm PVC had laid. Out of 150 FHTC, 28 HTC had given. Road cutting (1.8 km) issue is pending and due to which FHTC is not increasing at a faster rate. | Areacode AE | |
27 Dec 2022 | Pipe laying and HTC Connection work in progress | Areacode AE | |
19 Dec 2022 | Pipe laying and HTC Connection work in progress | Areacode AE | |
12 Dec 2022 | Pipe laying and HTC Connection work in progress | Areacode AE |