Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
07 Jun 2023 | will work almost complete. | Areacode AE | |
03 Jun 2023 | will work almost complete. | Areacode AE | |
30 May 2023 | will work almost complete. | Areacode AE | |
27 May 2023 | will work almost complete. | Areacode AE | |
23 May 2023 | will work almost complete. | Areacode AE | |
19 May 2023 | will work allmost complete. | Areacode AE | |
15 May 2023 | will work allmost complete. | Areacode AE | |
08 May 2023 | will work allmost complete. | Areacode AE | |
02 May 2023 | Tank concreting completed. Well depth reached up to 5.5 m and found rock. | Areacode AE | |
24 Apr 2023 | Tank concreting completed. Well depth reached up to 5.5 m and found rock. | Areacode AE |