Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
26 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
22 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
21 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
20 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
19 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
18 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. . Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
15 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. . Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
14 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. . Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE
12 Jun 2024 Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. . Work ongoing pipe laying progress and road restoration progress. Thrissur PH Dn EE