Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. . Work ongoing pipe laying progress and road restoration progress | Thrissur PH Dn EE | |
22 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. . Work ongoing pipe laying progress and road restoration progress | Thrissur PH Dn EE | |
21 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1048 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
18 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
17 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
16 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
15 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
14 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
13 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
10 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE |