Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
08 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
07 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
06 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
03 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
02 May 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
30 Apr 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
29 Apr 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
27 Apr 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
25 Apr 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE |