Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Apr 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
30 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
27 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
26 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
25 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
20 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
16 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
15 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing. | Thrissur PH Dn EE | |
14 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 1024 FHTCs provided. Geo tagging ongoing | Thrissur PH Dn EE | |
11 Mar 2024 | Work Order issued on 10/10/2022. Agreement executed on 25/10/2022. 958 FHTCs provided. Geo tagging ongoing | Thrissur PH Dn EE |