Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Feb 2022 | 128 FHTCs completed out of 2300,2nd and Part bill submitted | Vadanappilly AE | |
21 Feb 2022 | 98 FHTCs completed out of 2300,2nd and Part bill submitted | Vadanappilly AE | |
16 Feb 2022 | 88 FHTCs completed out of 2300,First and Part bill submitted | Vadanappilly AE | |
14 Feb 2022 | 67 FHTCs completed out of 2300,First and Part bill submitted | Vadanappilly AE | |
10 Feb 2022 | 51 FHTCs completed out of 2300,First and Part bill submitted | Vadanappilly AE | |
07 Feb 2022 | 51 FHTCs completed out of 2300,First and Part bill submitted | Vadanappilly AE | |
03 Feb 2022 | 44 FHTCs completed out of 2300,First and Part bill submitted | Vadanappilly AE | |
31 Jan 2022 | 44 FHTCs completed out of 2300,First and Part bill submitted | Vadanappilly AE | |
27 Jan 2022 | 31 FHTCs completed out of 2300,First and Part bill submitted | Vadanappilly AE | |
24 Jan 2022 | 31 FHTCs completed out of 2300,First and Part bill submitted | Vadanappilly AE |