Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Apr 2023 Work splitted in 2 packages and is submitted for TS approval Thiruvananthapuram Project AE2
24 Jan 2023 Work order issued. Due to higher quote the decision is pending with Govt of Kerala Thiruvananthapuram Project AE2
12 Sep 2022 Work order issued to Chicago construction. Work Order No KWA/PHC/D2/896/2017 Dated: 27.04.2022 of SE, PHC, Thiruvananthapuram. Thiruvananthapuram Project AE2
18 Apr 2022 Price bid opened on 8/04/22. Letter under processing from SE PHC to submit price bid to CE SR Thiruvananthapuram Project AE2
18 Apr 2022 For packages except for weir work retendered. The single bidder was technically prequalified as per the minutes of CE (SR) vide STC- TA conducted on 02.04.2022 Thiruvananthapuram Project AE2
16 Mar 2022 Package Weir across neyyar river- work tendered. For all other packages including well,WTP, pipelines & OHSRs, the work retendered with due date on 22-03-22 Thiruvananthapuram Project AE2
07 Mar 2022 STC held on 5-02-2022 and submitted for further clarifications Thiruvananthapuram Project AE2
12 Feb 2022 STC held on 5-02-2022 and submitted for further clarifications from SE. Out of 3 bidders only 1 qualified. Regarding the second bid further clarifications required. Thiruvananthapuram Project AE2
01 Feb 2022 bid document submitted to CE (SR) for technical prequalification Thiruvananthapuram Project AE2
01 Feb 2022 Tender document under scrutiny for technical prequalification Thiruvananthapuram Project AE2