Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Feb 2022 | Tender document under scrutiny for technical prequalification | Thiruvananthapuram Project AE2 | |
10 Jan 2022 | Tender document under scrutiny for technical prequalification | Thiruvananthapuram Project AE2 | |
04 Jan 2022 | 3 offers received. Bid opening on 5-01-2022 | Thiruvananthapuram Project AE2 | |
03 Jan 2022 | Work tendered. Tender extended up to 03-01-2022 | Thiruvananthapuram Project AE2 | |
28 Nov 2021 | TS obtained and Tender notice issued. Tender due date is on 20-12-21 | Thiruvananthapuram Project AE2 | |
28 Oct 2021 | TS obtained for 2 estimates. 1. Estimation of Transformer and allied works,supplying and installation of Raw Water Pumpset and,Clear water pumpsets 2. Estimation of Substation Building Civil works & compound wall | Thiruvananthapuram Project AE2 | |
28 Oct 2021 | Road restoration estimate obtained from PWD on 9-04-21 and accordingly P/M & T/M estimates were created. On 26-08-21 the land for WTP at Ponvilla was handed over to KWA by Revenue authorities | Thiruvananthapuram Project AE2 | |
25 Sep 2021 | estimates under scrutiny. Estimates revised with DSR 2018 | Thiruvananthapuram Project AE2 | |
13 Sep 2021 | estimates under scrutiny. Estimates revised with DSR 2018 | Thiruvananthapuram Project AE2 | |
08 Sep 2021 | The estimate prepared for TS under scrutiny. Estimate revised with DSR 2018. | Thiruvananthapuram Project AE2 |