12 Nov 2021 FHTC Geotagged-2675nos(geotagged today=0nos) FHTC total-2680Nos(today physical connection-0nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
10 Nov 2021 FHTC Geotagged-2664nos(geotagged today=45nos) FHTC total-2675Nos(today physical connection-52nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
09 Nov 2021 FHTC Geotagged-2619nos(geotagged today=25nos) FHTC total-2623Nos(today physical connection-25nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
08 Nov 2021 FHTC Geotagged-2594nos(geotagged today=16nos) FHTC total-2598Nos(today physical connection-20nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
06 Nov 2021 FHTC Geotagged-2578nos(geotagged today=10nos) FHTC total-2578Nos(today physical connection-07nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
05 Nov 2021 FHTC Geotagged-2568nos(geotagged today=11nos) FHTC total-2571Nos(today physical connection-11nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
04 Nov 2021 FHTC Geotagged-2557nos(geotagged today=15nos) FHTC total-2560Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
04 Nov 2021 FHTC Geotagged-2557nos(geotagged today=15nos) FHTC total-2550Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
03 Nov 2021 FHTC Geotagged-2542nos(geotagged today=22nos) FHTC total-2546Nos(today physical connection-11nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE
02 Nov 2021 FHTC Geotagged-2520nos(geotagged today=14nos) FHTC total-2532Nos(today physical connection-2nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE