Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Nov 2021 FHTC Geotagged-2804nos(geotagged today=19nos) FHTC total-2804Nos(today physical connection-19nos)Total pipe laid 11km , pressure testing done-6km- Kollam Project Dn AE
23 Nov 2021 FHTC Geotagged-2785nos(geotagged today=14nos) FHTC total-2785Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6km- Kollam Project Dn AE
22 Nov 2021 FHTC Geotagged-2771nos(geotagged today=14nos) FHTC total-2771Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6km- Kollam Project Dn AE
20 Nov 2021 FHTC Geotagged-2757nos(geotagged today=14nos) FHTC total-2757Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6km-work delayed due to rain Kollam Project Dn AE
19 Nov 2021 FHTC Geotagged-2743nos(geotagged today=13nos) FHTC total-2743Nos(today physical connection-13nos)Total pipe laid 11km , pressure testing done-6km-work delayed due to rain Kollam Project Dn AE
18 Nov 2021 FHTC Geotagged-2730nos(geotagged today=16nos) FHTC total-2730Nos(today physical connection-16nos)Total pipe laid 11km , pressure testing done-6km Kollam Project Dn AE
17 Nov 2021 FHTC Geotagged-2714nos(geotagged today=15nos) FHTC total-2714Nos(today physical connection-15nos)Total pipe laid 11km , pressure testing done-6km Kollam Project Dn AE
16 Nov 2021 FHTC Geotagged-2699nos(geotagged today=14nos) FHTC total-2699Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6 km-work is delaying de to heavy rain Kollam Project Dn AE
15 Nov 2021 FHTC Geotagged-2685nos(geotagged today=10nos) FHTC total-2685Nos(today physical connection-5nos)Total pipe laid 11km , pressure testing done-6 km-work is delaying de to heavy rain Kollam Project Dn AE
13 Nov 2021 Today no work due to heavy rain FHTC Geotagged-2675nos(geotagged today=0nos) FHTC total-2680Nos(today physical connection-0nos)Total pipe laid 11km , pressure testing done-6 km Kollam Project Dn AE