Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Nov 2021 | FHTC Geotagged-2804nos(geotagged today=19nos) FHTC total-2804Nos(today physical connection-19nos)Total pipe laid 11km , pressure testing done-6km- | Kollam Project Dn AE | |
23 Nov 2021 | FHTC Geotagged-2785nos(geotagged today=14nos) FHTC total-2785Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6km- | Kollam Project Dn AE | |
22 Nov 2021 | FHTC Geotagged-2771nos(geotagged today=14nos) FHTC total-2771Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6km- | Kollam Project Dn AE | |
20 Nov 2021 | FHTC Geotagged-2757nos(geotagged today=14nos) FHTC total-2757Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6km-work delayed due to rain | Kollam Project Dn AE | |
19 Nov 2021 | FHTC Geotagged-2743nos(geotagged today=13nos) FHTC total-2743Nos(today physical connection-13nos)Total pipe laid 11km , pressure testing done-6km-work delayed due to rain | Kollam Project Dn AE | |
18 Nov 2021 | FHTC Geotagged-2730nos(geotagged today=16nos) FHTC total-2730Nos(today physical connection-16nos)Total pipe laid 11km , pressure testing done-6km | Kollam Project Dn AE | |
17 Nov 2021 | FHTC Geotagged-2714nos(geotagged today=15nos) FHTC total-2714Nos(today physical connection-15nos)Total pipe laid 11km , pressure testing done-6km | Kollam Project Dn AE | |
16 Nov 2021 | FHTC Geotagged-2699nos(geotagged today=14nos) FHTC total-2699Nos(today physical connection-14nos)Total pipe laid 11km , pressure testing done-6 km-work is delaying de to heavy rain | Kollam Project Dn AE | |
15 Nov 2021 | FHTC Geotagged-2685nos(geotagged today=10nos) FHTC total-2685Nos(today physical connection-5nos)Total pipe laid 11km , pressure testing done-6 km-work is delaying de to heavy rain | Kollam Project Dn AE | |
13 Nov 2021 | Today no work due to heavy rain FHTC Geotagged-2675nos(geotagged today=0nos) FHTC total-2680Nos(today physical connection-0nos)Total pipe laid 11km , pressure testing done-6 km | Kollam Project Dn AE |