Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Feb 2022 | FHTC Geotagged-3320nos(geotagged today=3nos) FHTC total-3362Nos(today physical connection-03nos)Total pipe laid 19km , pressure testing done-12km | Kollam Project Dn AE | |
14 Feb 2022 | FHTC Geotagged-3317nos(geotagged today=2nos) FHTC total-3359Nos(today physical connection-10nos)Total pipe laid 19km , pressure testing done-12km | Kollam Project Dn AE | |
12 Feb 2022 | FHTC Geotagged-3315nos(geotagged today=0nos) FHTC total-3349Nos(today physical connection-5nos)Total pipe laid 19km , pressure testing done-12km | Kollam Project Dn AE | |
11 Feb 2022 | FHTC Geotagged-3315nos(geotagged today=8nos) FHTC total-3344Nos(today physical connection-8nos)Total pipe laid 18km , pressure testing done-12km | Kollam Project Dn AE | |
10 Feb 2022 | FHTC Geotagged-3307nos(geotagged today=3nos) FHTC total-3336Nos(today physical connection-3nos)Total pipe laid 18km , pressure testing done-12km | Kollam Project Dn AE | |
09 Feb 2022 | FHTC Geotagged-3304nos(geotagged today=6nos) FHTC total-3333Nos(today physical connection-6nos)Total pipe laid 18km , pressure testing done-12km | Kollam Project Dn AE | |
08 Feb 2022 | FHTC Geotagged-3298nos(geotagged today=7nos) FHTC total-3327Nos(today physical connection-7nos)Total pipe laid 18km , pressure testing done-12km | Kollam Project Dn AE | |
07 Feb 2022 | FHTC Geotagged-3291nos(geotagged today=11nos) FHTC total-3320Nos(today physical connection-11nos)Total pipe laid 18km , pressure testing done-12km | Kollam Project Dn AE | |
06 Feb 2022 | FHTC Geotagged-3280nos(geotagged today=0nos) FHTC total-3309Nos(today physical connection-0nos)Total pipe laid 18km , pressure testing done-12km | Kollam Project Dn AE | |
05 Feb 2022 | FHTC Geotagged-3280nos(geotagged today=17nos) FHTC total-3309Nos(today physical connection-17nos)Total pipe laid 18km , pressure testing done-12km | Kollam Project Dn AE |