Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Apr 2022 FHTC Geotagged-3710 nos(geotagged today= 10 nos) FHTC total-3710 Nos(today physical connection- 10 nos)Total pipe laid 23km Kollam Project Dn AE
01 Apr 2022 FHTC Geotagged-3700 nos(geotagged today= 05 nos) FHTC total-3700 Nos(today physical connection- 05 nos)Total pipe laid 23km Kollam Project Dn AE
31 Mar 2022 FHTC Geotagged-3695nos(geotagged today= 05 nos) FHTC total-3695Nos(today physical connection- 05 nos)Total pipe laid 23km Kollam Project Dn AE
30 Mar 2022 FHTC Geotagged-3690 nos(geotagged today= 19 nos) FHTC total-3690 Nos(today physical connection- 19 nos)Total pipe laid 23km Kollam Project Dn AE
29 Mar 2022 FHTC Geotagged-3671nos(geotagged today= 0 nos) FHTC total-3671 Nos(today physical connection- 0 nos)Total pipe laid 22km Kollam Project Dn AE
28 Mar 2022 FHTC Geotagged-3671nos(geotagged today= 0 nos) FHTC total-3671 Nos(today physical connection- 0 nos)Total pipe laid 22km Kollam Project Dn AE
26 Mar 2022 FHTC Geotagged-3671nos(geotagged today= 16 nos) FHTC total-3671 Nos(today physical connection- 16 nos)Total pipe laid 22km Kollam Project Dn AE
25 Mar 2022 FHTC Geotagged-3655nos(geotagged today= 16 nos) FHTC total-3655 Nos(today physical connection- 16 nos)Total pipe laid 22km Kollam Project Dn AE
24 Mar 2022 FHTC Geotagged-3639nos(geotagged today= 15 nos) FHTC total-3639 Nos(today physical connection- 15 nos)Total pipe laid 22km Kollam Project Dn AE
23 Mar 2022 FHTC Geotagged-3624 nos(geotagged today= 13 nos) FHTC total-3624 Nos(today physical connection- 13 nos)Total pipe laid 22km Kollam Project Dn AE