| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 May 2022 | Work temporarily halted due to rain . | Plamoodu Sewerage Project Sn AE | |
| 20 May 2022 | Work temporarily halted due to rain . | Plamoodu Sewerage Project Sn AE | |
| 19 May 2022 | Work temporarily halted due to rain . | Plamoodu Sewerage Project Sn AE | |
| 17 May 2022 | Work temporarily halted due to rain . | Plamoodu Sewerage Project Sn AE | |
| 16 May 2022 | Work temporarily halted due to rain | Plamoodu Sewerage Project Sn AE | |
| 14 May 2022 | Excavation and pipe laying work towards main road is in progress. 455 m pipe laid and 30 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 13 May 2022 | Excavation and pipe laying work towards main road is in progress. 450 m pipe laid and 30 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 12 May 2022 | Excavation and pipe laying work towards main road is in progress. 475 m pipe laid and 30 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 09 May 2022 | Today there was no work . | Plamoodu Sewerage Project Sn AE | |
| 07 May 2022 | Excavation and demolishing of drain is in progress. | Plamoodu Sewerage Project Sn AE |