| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Jul 2022 | Work temporary halted due to rain | Plamoodu Sewerage Project Sn AE | |
| 16 Jul 2022 | pipe laying work is in progress | Plamoodu Sewerage Project Sn AE | |
| 14 Jul 2022 | 612 m pipe laid and 33 MH casted and 1 MH is under construction. | Plamoodu Sewerage Project Sn AE | |
| 12 Jul 2022 | Excavation and pipe laying work towards main road is in progress. 608 m pipe laid and 33 MH casted and 1 MH under construction. | Plamoodu Sewerage Project Sn AE | |
| 06 Jul 2022 | Excavation and pipe laying work towards main road is in progress. 608 m pipe laid and 33 MH casted and 1 MH under construction. | Plamoodu Sewerage Project Sn AE | |
| 02 Jul 2022 | Excavation and pipe laying work towards main road is in progress. 608 m pipe laid and 33 MH casted and 1 MH under construction. | Plamoodu Sewerage Project Sn AE | |
| 30 Jun 2022 | Excavation and pipe laying work towards main road is in progress. 608 m pipe laid and 33 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 28 Jun 2022 | Excavation and pipe laying work towards main road is in progress. 608 m pipe laid and 33 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 27 Jun 2022 | Excavation and pipe laying work towards main road is in progress. 605 m pipe laid and 33 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 25 Jun 2022 | Excavation and pipe laying work towards main road is in progress. 585 m pipe laid and 33 MH casted. | Plamoodu Sewerage Project Sn AE |