| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Mar 2022 | Excavation and pipe laying work in second branch line is in progress.230 m pipe laid and 12 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 21 Mar 2022 | Excavation and pipe laying work in second branch line is in progress.220 m pipe laid and 12 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 18 Mar 2022 | Excavation and pipe laying work in second branch line is in progress. | Plamoodu Sewerage Project Sn AE | |
| 15 Mar 2022 | Excavation and pipe in second branch is in progress. | Plamoodu Sewerage Project Sn AE | |
| 14 Mar 2022 | Excavation in second branch is in progress. | Plamoodu Sewerage Project Sn AE | |
| 11 Mar 2022 | No work due to nearby temple festival. | Plamoodu Sewerage Project Sn AE | |
| 10 Mar 2022 | No work due to nearby temple festival. | Plamoodu Sewerage Project Sn AE | |
| 09 Mar 2022 | No work due to nearby temple festival. | Plamoodu Sewerage Project Sn AE | |
| 07 Mar 2022 | pipe line work completed up to 185 meters . 10MH completed.Material arrangements for second line is in progress . | Plamoodu Sewerage Project Sn AE | |
| 04 Mar 2022 | pipe line work completed up to 185 meters . 10MH completed. | Plamoodu Sewerage Project Sn AE |