| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Aug 2022 | 670 m pipe laid and 39 MH casted and 1 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 12 Aug 2022 | 660 m pipe laid and 38 MH casted and 1 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 09 Aug 2022 | 650 m pipe laid and 37 MH casted and 1 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 06 Aug 2022 | 640 m pipe laid and 36 MH casted and 1 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 03 Aug 2022 | Work temporary halted due to rain | Plamoodu Sewerage Project Sn AE | |
| 01 Aug 2022 | 640 m pipe laid and 34 MH casted and 1 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 27 Jul 2022 | 640 m pipe laid and 33 MH casted and 2 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 25 Jul 2022 | 630 m pipe laid and 33 MH casted and 2 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 21 Jul 2022 | 615 m pipe laid and 33 MH casted and 1 MH is under construction | Plamoodu Sewerage Project Sn AE | |
| 20 Jul 2022 | Excavation and pipe laying work towards main road is in progress. 608 m pipe laid and 33 MH casted and 1 MH under construction. | Plamoodu Sewerage Project Sn AE |