| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Apr 2022 | Excavation and pipe laying work towards main road is in progress.375 m pipe laid and 20 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 08 Apr 2022 | Excavation and pipe laying work towards main road is in progress.368 m pipe laid and 19 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 07 Apr 2022 | Excavation and pipe laying work towards main road is in progress.355 m pipe laid and 19 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 05 Apr 2022 | Excavation and pipe laying work towards main road is in progress.340 m pipe laid and 18 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 04 Apr 2022 | Excavation and pipe laying work towards main road is in progress.325 m pipe laid and 18 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 02 Apr 2022 | Excavation and pipe laying work in second branch line is in progress.285m pipe laid and 17 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 01 Apr 2022 | Excavation and pipe laying work in second branch line is in progress.270 m pipe laid and 15 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 30 Mar 2022 | Excavation and pipe laying work in second branch line is in progress.240 m pipe laid and 14 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 29 Mar 2022 | Excavation and pipe laying work in second branch line is in progress.240 m pipe laid and 14 MH casted. | Plamoodu Sewerage Project Sn AE | |
| 25 Mar 2022 | Excavation and pipe laying work in second branch line is in progress.235 m pipe laid and 13 MH casted. | Plamoodu Sewerage Project Sn AE |