Status Date |
Overall Project Status |
Project Officer |
Contact |
18 Feb 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
17 Feb 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
09 Feb 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, drawings of 4 panchayath submitted and other 4 panchayath drawings are under preparation |
Malappuram Project Dn AE6 |
|
05 Feb 2021 |
overall 19 percentage of work completed, package 1-16 km of distribution pipe line laid, package 2-3 km of pipe line laid, package 3 - 2.5 km of distribution pipe line laid, package-4 , survey completed, drawing under preparation |
Malappuram Project Dn AE6 |
|
25 Jan 2021 |
oveall 18 percentage of work completed |
Malappuram Project Dn AE6 |
|
31 Dec 2020 |
overall 17 percentage of work completed |
Malappuram Project Dn AE6 |
|
18 Dec 2020 |
overall 15 percentage of work completed |
Malappuram Project Dn AE6 |
|
17 Nov 2020 |
5 percentage of the work completed, package 4 -conducting survey 90 percentage of the work completed, |
Malappuram Project Dn AE6 |
|