Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Feb 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
17 Feb 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
09 Feb 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, drawings of 4 panchayath submitted and other 4 panchayath drawings are under preparation Malappuram Project Dn AE6
05 Feb 2021 overall 19 percentage of work completed, package 1-16 km of distribution pipe line laid, package 2-3 km of pipe line laid, package 3 - 2.5 km of distribution pipe line laid, package-4 , survey completed, drawing under preparation Malappuram Project Dn AE6
25 Jan 2021 oveall 18 percentage of work completed Malappuram Project Dn AE6
31 Dec 2020 overall 17 percentage of work completed Malappuram Project Dn AE6
18 Dec 2020 overall 15 percentage of work completed Malappuram Project Dn AE6
17 Nov 2020 5 percentage of the work completed, package 4 -conducting survey 90 percentage of the work completed, Malappuram Project Dn AE6