Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Jan 2022 |
pvc pipe laying work in progress and overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
21 Dec 2021 |
pvc pipe laying work in progress and overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
30 Nov 2021 |
pvc pipe laying work in progress and overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
22 Nov 2021 |
pvc pipe laying work in progress and overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
19 Nov 2021 |
pvc pipe laying work in progress and overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
18 Nov 2021 |
pvc pipe laying work in progress and overall 50 percentage of work completed |
Malappuram Project Dn AE6 |
|
25 Sep 2021 |
package 1-38 km of distribution pipe line laid, package 2-26 km of pipe line laid, package 3 - 5 km of distribution pipe line laid, package-4 , survey completed |
Malappuram Project Dn AE6 |
|
26 Aug 2021 |
package 1-38 km of distribution pipe line laid, package 2-26 km of pipe line laid, package 3 - 5 km of distribution pipe line laid, package-4 , survey completed |
Malappuram Project Dn AE6 |
|
07 Jun 2021 |
package 1-38 km of distribution pipe line laid, package 2-26 km of pipe line laid, package 3 - 5 km of distribution pipe line laid, package-4 , survey completed, |
Malappuram Project Dn AE6 |
|
12 May 2021 |
package 1-25 km of distribution pipe line laid, package 2-9 km of pipe line laid, package 3 - 4 km of distribution pipe line laid, package-4 , survey completed, |
Malappuram Project Dn AE6 |
|