20 May 2024 State Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Package II(a)- Balance distribution to Vazhakkad Panchayaths-Pipeline Work started tate Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Package II(B2)- Supply and laying distribution system- distribution work started State Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Package II(B3)- Laying 160 mm PVC Pipe along Pengad alungal PWD road - connection work started State Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Package II(B4)- LSGD Road restoration - road restoration started State Plan-2019-20 Rural Water supply schemes. Water supply scheme to Cheekode and adjoining villages Phase II-Package II(B1)- Providing and Fixing GI Pipes and interconnection with existing pipe line - GI work started Malappuram Project Dn AE6
11 Jul 2023 The work short closed as the lack of road cutting permission from PWD and shortage of GI pipe in rural concrete roads also the contractor not willing to execute the work in time extension. Estimate for the Balance works and FHTCs prepared and submitted. Malappuram Project Dn AE6
15 Jun 2023 Inter connection work and house connection works on going Malappuram Project Dn AE6
24 May 2023 Inter connection work and house connection works on going Malappuram Project Dn AE6
11 May 2023 Inter connection work and house connection works on going Malappuram Project Dn AE6
05 May 2023 Inter connection work and house connection works on going Malappuram Project Dn AE6
20 Apr 2023 inter connection work and house connection works on going Malappuram Project Dn AE6
23 Aug 2022 pvc pipe laying work in progress, overall 68 percentage of work completed Malappuram Project Dn AE6
07 Jul 2022 pvc pipe laying work in progress, overall 67 percentage of work completed Malappuram Project Dn AE6
13 Jun 2022 pvc pipe laying work in progress, overall 66 percentage of work completed Malappuram Project Dn AE6