Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Mar 2021 package 1-19 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
15 Mar 2021 overall 20 percentage of work completed, package 1-19 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
09 Mar 2021 overall 20 percentage of work completed, package 1-19 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
07 Mar 2021 overall 20 percentage of work completed, package 1-19 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
01 Mar 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
26 Feb 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
25 Feb 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
24 Feb 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
23 Feb 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6
20 Feb 2021 overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification Malappuram Project Dn AE6