Status Date |
Overall Project Status |
Project Officer |
Contact |
16 Mar 2021 |
package 1-19 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
15 Mar 2021 |
overall 20 percentage of work completed, package 1-19 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
09 Mar 2021 |
overall 20 percentage of work completed, package 1-19 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
07 Mar 2021 |
overall 20 percentage of work completed, package 1-19 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
01 Mar 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
26 Feb 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
25 Feb 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
24 Feb 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
23 Feb 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|
20 Feb 2021 |
overall 20 percentage of work completed, package 1-17 km of distribution pipe line laid, package 2-4 km of pipe line laid, package 3 - 3 km of distribution pipe line laid, package-4 , survey completed, 8 panchayath drawing submitted fro verification |
Malappuram Project Dn AE6 |
|