Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Jun 2024 | 14th and Final Bill submitted. Work Short closed | Vadanappilly AE | |
12 Jun 2024 | 14th and Final Bill submitted. Work Short closed | Vadanappilly AE | |
27 Apr 2024 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. | Vadanappilly AE | |
20 Apr 2024 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. | Nattika AEE | |
18 Apr 2024 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. | Vadanappilly AE | |
08 Apr 2024 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. | Vadanappilly AE | |
25 Mar 2024 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. | Vadanappilly AE | |
19 Mar 2024 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. | Vadanappilly AE | |
14 Mar 2024 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. | Vadanappilly AE | |
29 Feb 2024 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. | Vadanappilly AE |