- Home
- Jal Jeevan Mission- 2020-21- Phase I - V...
Jal Jeevan Mission- 2020-21- Phase I - Valapad Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS)
Project |
Jal Jeevan Mission- 2020-21- Phase I - Valapad Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Project Code |
TCRJJM08205242 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission- 2020-21- Phase I - Valapad Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Status |
Short Closed |
District |
Thrissur |
Executing Office |
Vadanappalli Sn |
AS Amount (Rs) |
174600000
|
AS Number |
GO(Rt) No 541/2020/WRD |
TS Amount (Rs) |
138660000 |
TS Number |
TS/2020-2021/2020/21871 |
Total Bill Submitted (Rs) |
165266190 |
Total Bill Paid (Rs) |
165266190 |
Population Benefitted |
50000 |
Capacity in MLD |
20.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Valapad Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission- 2020-21- Phase I - Valapad Grama Panchayath- Providing FHTC to Rural house holds by augmentation of existing schemes and by ongoing schemes (MVS) |
Vadanappalli Sn |
|
2 |
Jal Jeevan Mission Phase I - Valapad Grama Panchayath- CWSS to Nattika Firka- Providing FHTC to Rural house holds |
Vadanappalli Sn |
|
3 |
JJM - 2020-21 - Valappad PANCHAYATH- Providing public tap based FHTC to Rural house holds.-PART 1 (30 Nos) |
PH.Division Irinjalakkuda |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
14th and Final Bill submitted. Work Short closed |
Vadanappilly AE |
|
12 Jun 2024 |
14th and Final Bill submitted. Work Short closed |
Vadanappilly AE |
|
27 Apr 2024 |
1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. |
Vadanappilly AE |
|
20 Apr 2024 |
1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. |
Nattika AEE |
|
18 Apr 2024 |
1559 connections completed out of 4400 (FHTC -1477 and 82htc), 13th Part bill submitted. |
Vadanappilly AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
24/08/2020 |
Scheduled date of Completion of the Project |
31 Mar 2021 |
Expected date of Completion |
30/06/2023 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
22 Oct 2020 |