Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Oct 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 12th Part bill submitted. | Vadanappilly AE | |
25 Oct 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 12th Part bill submitted. | Vadanappilly AE | |
19 Oct 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc), 12th Part bill submitted. | Vadanappilly AE | |
16 Oct 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
12 Oct 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
09 Oct 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
05 Oct 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
03 Oct 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
29 Sep 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
25 Sep 2023 | 1559 connections completed out of 4400 (FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE |