Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Aug 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
17 Aug 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
14 Aug 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted. | Vadanappilly AE | |
10 Aug 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted | Vadanappilly AE | |
07 Aug 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted | Vadanappilly AE | |
03 Aug 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted | Vadanappilly AE | |
31 Jul 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted | Vadanappilly AE | |
27 Jul 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted | Vadanappilly AE | |
24 Jul 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted | Vadanappilly AE | |
20 Jul 2023 | 1559connections completed out of 4400(FHTC -1477 and 82htc) , 12th Part bill submitted | Vadanappilly AE |