| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Jan 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. | Chathannur PH Sn AE | |
| 03 Jan 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. | Chathannur PH Sn AE | |
| 01 Jan 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Repalcement of damaged connections- 100no.s completed. | Chathannur PH Sn AE | |
| 31 Dec 2024 | Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. | Chathannur PH Sn AE | |
| 23 Dec 2024 | Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. | Chathannur PH Sn AE | |
| 18 Dec 2024 | Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. | Chathannur PH Sn AE | |
| 16 Dec 2024 | Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. | Chathannur PH Sn AE | |
| 13 Dec 2024 | Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. | Chathannur PH Sn AE | |
| 11 Dec 2024 | Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. | Chathannur PH Sn AE | |
| 10 Dec 2024 | Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing | Chathannur PH Sn AE |