Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Jan 2025 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Chathannur PH Sn AE
03 Jan 2025 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Chathannur PH Sn AE
01 Jan 2025 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Repalcement of damaged connections- 100no.s completed. Chathannur PH Sn AE
31 Dec 2024 Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. Chathannur PH Sn AE
23 Dec 2024 Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. Chathannur PH Sn AE
18 Dec 2024 Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. Chathannur PH Sn AE
16 Dec 2024 Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. Chathannur PH Sn AE
13 Dec 2024 Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. Chathannur PH Sn AE
11 Dec 2024 Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing. Chathannur PH Sn AE
10 Dec 2024 Road cutting permission obtained from PWD. 90mm PVC pipe line laying work ongoing Chathannur PH Sn AE