| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Nov 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 08 Nov 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 07 Nov 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 06 Nov 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 05 Nov 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 04 Nov 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 02 Nov 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 01 Nov 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 29 Oct 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE | |
| 28 Oct 2024 | Road cutting permission not obtained from PWD | Chathannur PH Sn AE |