| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 47 No.s. Geotagging of water connections -47No.s | Chathannur PH Sn AE | |
| 22 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s. Geotagging of water connections -45 No.s | Chathannur PH Sn AE | |
| 20 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s. Geotagging of water connections -45 No.s | Chathannur PH Sn AE | |
| 19 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s. Geotagging of water connections -45 No.s | Chathannur PH Sn AE | |
| 18 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s . Geotagging of water connections -45 No.s | Chathannur PH Sn AE | |
| 17 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s . Geotagging of water connections -45 No.s | Chathannur PH Sn AE | |
| 17 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s . Geotagging of water connections -45 No.s | Chathannur PH Sn AE | |
| 15 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s . Geotagging of water connections -45 No.s | Chathannur PH Sn AE | |
| 14 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s . Geotagging of water connections -45 No.s | Chathannur PH Sn AE | |
| 12 Feb 2025 | 90mm PVC pipe laying work in progress -1014m completed. 75mm PVC pipe laying work in progress -775mcompleted. Providing and fixing 65mm G.I pipe - 500m completed. Supply of 80mm G.I pipe- 500m completed. Replacement of damaged connections- 100no.s completed. Providing FHTCs from the existing water supply scheme work ongoing- 45 No.s . Geotagging of water connections -45 No.s | Chathannur PH Sn AE |