| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Oct 2024 | Road cutting permission not obtained from PWD. | Chathannur PH Sn AE | |
| 15 Oct 2024 | Road cutting permission not obtained from PWD. | Chathannur PH Sn AE | |
| 14 Oct 2024 | Road cutting permission not obtained from PWD. | Chathannur PH Sn AE | |
| 10 Oct 2024 | Road cutting permission not obtained from PWD. | Chathannur PH Sn AE | |
| 09 Oct 2024 | Road cutting permission not obtained from PWD. | Chathannur PH Sn AE | |
| 08 Oct 2024 | Road cutting permission not obtained from PWD. | Chathannur PH Sn AE | |
| 07 Oct 2024 | Pipe laying work ongoing. 950m ,90mm PVC pipe and 440m, 75mm pipe laid | Chathannur PH Sn AE | |
| 05 Oct 2024 | Pipe laying work ongoing. 950m ,90mm PVC pipe and 440m, 75mm pipe laid | Chathannur PH Sn AE | |
| 04 Oct 2024 | Pipe laying work ongoing. 950m ,90mm PVC pipe and 440m, 75mm pipe laid | Chathannur PH Sn AE | |
| 03 Oct 2024 | Pipe laying work ongoing. 950m ,90mm PVC pipe and 440m, 75mm pipe laid | Chathannur PH Sn AE |