Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
21 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 35 FHTCs given. Tagging on going-62% But Work stopped due to rain | Thrissur PH Dn EE | |
20 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% But Work stopped due to rain | Thrissur PH Dn EE | |
19 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% But Work stopped due to rain | Thrissur PH Dn EE | |
17 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% But Work stopped due to rain on 16.06.2023 | Thrissur PH Dn EE | |
15 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% But Work stopped due to rain on 14.06.2023 | Thrissur PH Dn EE | |
14 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% | Thrissur PH Dn EE | |
13 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% | Thrissur PH Dn EE | |
12 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% | Thrissur PH Dn EE | |
09 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% | Thrissur PH Dn EE | |
07 Jun 2023 | Pkg A-pipe laying work in progress-35% Pkg B-pipe laying work in progress-43% Pkg C- 25 FHTCs given. Balance work on going-62% | Thrissur PH Dn EE |