Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
16 Jun 2021 | Pipe expected to be received and work to commence by next week. | Malappuram Project Dn AE5 | |
01 Jun 2021 | Pipe expected to be received and work to commence by next week. | Malappuram Project Dn AE5 | |
26 May 2021 | Pipe expected to be received and work to commence by next week. | Malappuram Project Dn AE5 | |
05 May 2021 | Pipe expected to be received and work to commence by next week. | Malappuram Project Dn AE5 | |
26 Apr 2021 | Agreement executed, project did not start. There are no distribution lines in the Panchayath. This work is to be done along with main distribution network awarded under KIIFB. Pipes ordered. | Malappuram Project Dn AE5 | |
19 Apr 2021 | Agreement executed, project did not start. There are no distribution lines in the Panchayath. This work is to be done along with main distribution network awarded under KIIFB. Pipes ordered. | Malappuram Project Dn AE5 | |
13 Apr 2021 | Agreement executed, project did not start. There are no distribution lines in the Panchayath. This work is to be done along with main distribution network awarded under KIIFB. Pipes ordered. | Malappuram Project Dn AE5 | |
12 Apr 2021 | Agreement executed, project did not start. There are no distribution lines in the Panchayath. This work is to be done along with main distribution network awarded under KIIFB. Pipes ordered. | Malappuram Project Dn AE5 | |
09 Apr 2021 | Agreement executed, project did not start. There are no distribution lines in the Panchayath. This work is to be done along with main distribution network awarded under KIIFB. Pipes ordered. | Malappuram Project Dn AE5 | |
08 Apr 2021 | Agreement executed, project did not start. There are no distribution lines in the Panchayath. This work is to be done along with main distribution network awarded under KIIFB. Pipes ordered. | Malappuram Project Dn AE5 |