Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
20 Dec 2022 | Pipe laying work -98% completed. 5300 FHTCs provided. | Malappuram Project Dn AE3 | |
12 Dec 2022 | Pipe laying work -98% completed. 4808 FHTCs provided. | Malappuram Project Dn AE3 | |
16 Nov 2022 | Pipe laying work -98% completed. 4700 FHTCs provided. | Malappuram Project Dn AE3 | |
28 Oct 2022 | Pipe laying work -98% completed. 4480 FHTCs provided. | Malappuram Project Dn AE3 | |
18 Oct 2022 | Pipe laying work -98% completed. 4480 FHTCs provided. | Malappuram Project Dn AE3 | |
07 Oct 2022 | Pipe laying work -98% completed. 4400 FHTCs provided. | Malappuram Project Dn AE3 | |
28 Sep 2022 | Pipe laying work -98% completed. 4300 FHTCs provided. | Malappuram Project Dn AE3 | |
09 Sep 2022 | Pipe laying work -98% completed. 4012 FHTCs provided. | Malappuram Project Dn AE3 | |
22 Aug 2022 | Pipe laying work -98% completed. 3852 FHTCs provided. | Malappuram Project Dn AE5 | |
10 Aug 2022 | Pipe laying work -98% completed. 3752 FHTCs provided. | Malappuram Project Dn AE5 |