Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
22 Apr 2022 | 90 mm 10 kg PVC Pipes 10000 m laid. & 1695 Connections provided. | Malappuram Project Dn AE5 | |
20 Apr 2022 | 90 mm 10 kg PVC Pipes 10070 m laid. & 1458 Connections provided. | Malappuram Project Dn AE5 | |
11 Apr 2022 | 90 mm 10 kg PVC Pipes 9560 m laid. & 1458 Connections provided. | Malappuram Project Dn AE5 | |
31 Mar 2022 | 90 mm 10 kg PVC Pipes 8940 m laid. & 1458 Connections provided. | Malappuram Project Dn AE5 | |
24 Mar 2022 | 90 mm 10 kg PVC Pipes 8060 m laid. & 1450 Connections provided. | Malappuram Project Dn AE5 | |
22 Mar 2022 | 90 mm 10 kg PVC Pipes 8060 m laid. & 1232 Connections provided. | Malappuram Project Dn AE5 | |
18 Mar 2022 | Most of the distribution network were done in KIIFB work which was only started in August 2021. JJM Work is moving along with the KIIFB Work now. | Malappuram Project Dn AE5 | |
15 Mar 2022 | 90 mm 10 kg PVC Pipes 8060 m laid. & 1232 Connections provided | Malappuram Project Dn AE5 | |
07 Mar 2022 | 90 mm 10 kg PVC Pipes 8060 m laid. & 1222 Connections provided | Malappuram Project Dn AE5 | |
27 Feb 2022 | 90 mm 10 kg PVC Pipes 8060 m laid. & 895 Connections provided | Malappuram Project Dn AE5 |