Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Apr 2022 90 mm 10 kg PVC Pipes 10000 m laid. & 1695 Connections provided. Malappuram Project Dn AE5
20 Apr 2022 90 mm 10 kg PVC Pipes 10070 m laid. & 1458 Connections provided. Malappuram Project Dn AE5
11 Apr 2022 90 mm 10 kg PVC Pipes 9560 m laid. & 1458 Connections provided. Malappuram Project Dn AE5
31 Mar 2022 90 mm 10 kg PVC Pipes 8940 m laid. & 1458 Connections provided. Malappuram Project Dn AE5
24 Mar 2022 90 mm 10 kg PVC Pipes 8060 m laid. & 1450 Connections provided. Malappuram Project Dn AE5
22 Mar 2022 90 mm 10 kg PVC Pipes 8060 m laid. & 1232 Connections provided. Malappuram Project Dn AE5
18 Mar 2022 Most of the distribution network were done in KIIFB work which was only started in August 2021. JJM Work is moving along with the KIIFB Work now. Malappuram Project Dn AE5
15 Mar 2022 90 mm 10 kg PVC Pipes 8060 m laid. & 1232 Connections provided Malappuram Project Dn AE5
07 Mar 2022 90 mm 10 kg PVC Pipes 8060 m laid. & 1222 Connections provided Malappuram Project Dn AE5
27 Feb 2022 90 mm 10 kg PVC Pipes 8060 m laid. & 895 Connections provided Malappuram Project Dn AE5