Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Aug 2022 | Pipe laying work -98% completed. 3752 FHTCs provided | Malappuram Project Dn AE5 | |
23 Jul 2022 | Pipe laying work -98% completed. 3752 FHTCs provided | Malappuram Project Dn AE5 | |
13 Jul 2022 | Pipe laying work -98% completed. 3730 FHTCs provided | Malappuram Project Dn AE5 | |
29 Jun 2022 | Pipe laying work -98% completed. 3353 FHTCs provided | Malappuram Project Dn AE5 | |
20 Jun 2022 | Pipe laying work -98% completed. 2751 FHTCs provided | Malappuram Project Dn AE5 | |
10 Jun 2022 | Pipe laying work -98% completed. 2701 FHTCs provided | Malappuram Project Dn AE5 | |
30 May 2022 | 90 mm 10 kg PVC Pipes 10000 m laid. & 2601 Connections provided. | Malappuram Project Dn AE5 | |
20 May 2022 | 90 mm 10 kg PVC Pipes 10000 m laid. & 2528 Connections provided. | Malappuram Project Dn AE5 | |
10 May 2022 | 90 mm 10 kg PVC Pipes 10000 m laid. & 2528 Connections provided. | Malappuram Project Dn AE5 | |
29 Apr 2022 | 90 mm 10 kg PVC Pipes 10000 m laid. & 1988 Connections provided. | Malappuram Project Dn AE5 |