Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Dec 2021 90 mm 10 kg PVC Pipes 4200 m laid. & 65 Connections provided. Malappuram Project Dn AE5
02 Dec 2021 90 mm 10 kg PVC Pipes 3850 m laid. & 40 Connections provided. Malappuram Project Dn AE5
25 Nov 2021 90 mm 10 kg PVC Pipes 3750 m laid. & 12 Connections provided. Malappuram Project Dn AE5
19 Nov 2021 90 mm 10 kg PVC Pipes 3750 m laid. Malappuram Project Dn AE5
13 Nov 2021 90 mm 10 kg PVC Pipes 3750 m laid. Malappuram Project Dn AE5
18 Oct 2021 90 mm 10 kg PVC Pipes 3740 m laid. Malappuram Project Dn AE5
25 Sep 2021 90 mm 10 kg PVC Pipes 600 m laid. Malappuram Project Dn AE5
27 Aug 2021 Connections Started. Malappuram Project Dn AE5
12 Jul 2021 Pipe expected to be received and work to commence by next week. Malappuram Project Dn AE5
01 Jul 2021 Pipe expected to be received and work to commence by next week. Malappuram Project Dn AE5