Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm)with M25 concrete Total quantity of concrete used =1.616 m3 Nattika Project Dn AE 4
14 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed Nattika Project Dn AE 4
13 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case progressing. Nattika Project Dn AE 4
12 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case progressing.No of steps in first flight =8. rise = 15 cm and tread =24 cm. Nattika Project Dn AE 4
11 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Nattika Project Dn AE 4
10 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on. Nattika Project Dn AE 4
09 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed Nattika Project Dn AE 4
08 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.column concreting is done in 2 stages. concreting of 14 columns is completed.in the remaining 14 columns, 12 columns are concreted up to a height of 1.1 m and 2 columns are concreted up to a height of 0.9 m . Nattika Project Dn AE 4
07 Apr 2024 24 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed. concreting of 14 columns is completed Nattika Project Dn AE 4
06 Apr 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.column concreting is done in 2 stages. Haunch bars of 12mm dia is provided . Out of a total of 28 columns, concreting of 14 columns up to a height of 2 m is completed. Nattika Project Dn AE 4