Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Mar 2024 | Soil filling up to plinth level is performed | Nattika Project Dn AE 4 | |
14 Mar 2024 | Soil filling up to plinth level is performed | Nattika Project Dn AE 4 | |
13 Mar 2024 | Soil filling up to plinthlevel is performed | Nattika Project Dn AE 4 | |
12 Mar 2024 | Bar straightening for beams | Nattika Project Dn AE 4 | |
11 Mar 2024 | Column reinforcement and shuttering work ongoing | Nattika Project Dn AE 4 | |
10 Mar 2024 | Column reinforcement work and shuttering work ongoing | Nattika Project Dn AE 4 | |
08 Mar 2024 | Column reinforcement work, concreting,slump test ongoing | Nattika Project Dn AE 4 | |
07 Mar 2024 | Column reinforcement work ongoing | Nattika Project Dn AE 4 | |
06 Mar 2024 | Concreting of footing ongoing | Nattika Project Dn AE 4 | |