Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3.shuttering works for 2nd level beam and haunch progressing. Nattika Project Dn AE 4
24 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3.Steel reinforcement work & shuttering works ongoing. Nattika Project Dn AE 4
23 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3. Nattika Project Dn AE 4
22 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3.Steel reinforcement works for 2nd level beam ongoing. Nattika Project Dn AE 4
21 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3.Steel reinforcement works for 2nd level beam ongoing. Nattika Project Dn AE 4
20 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3.Steel reinforcement works for 2nd level beam ongoing. Nattika Project Dn AE 4
19 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3.Shuttering work for 2nd level beam is ongoing. Nattika Project Dn AE 4
18 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3. Nattika Project Dn AE 4
17 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3. Nattika Project Dn AE 4
16 Jun 2024 7 LL OHSR at AVANUR - Excavation completed. Site levelling done. Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed. Completed soil filling up to plinth level. Reinforcement work for plinth beam completed. Shuttering works for plinth beam concreting completed. Plinth beam concreting done. Overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column. Shuttering works for column concreting completed. Concreting of 28 columns are completed. Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab. Main bars of 10 mm diameter are given at top and bottom layers of landing slab. Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed. Total quantity of concrete used is 23.654 m3.concreting of 26 columns completed .Total quantity of concrete 8.95m3.concreting of 2 columns of height 60 cm done. Concreting of second flight and landing slab done. Total quantity of concrete used is 1.34m3. Nattika Project Dn AE 4