Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Mar 2024 | Column work in progress | Nattika Project Dn AE 4 | |
03 Mar 2024 | Concreting of footing ongoing | Nattika Project Dn AE 4 | |
02 Mar 2024 | Concreting of footing ongoing | Nattika Project Dn AE 4 | |
01 Mar 2024 | Concreting of footing started | Nattika Project Dn AE 4 | |
29 Feb 2024 | Shuttering work for footing | Nattika Project Dn AE 4 | |
28 Feb 2024 | Footing reinforcement work ongoing | Nattika Project Dn AE 4 | |
27 Feb 2024 | Concreting, curing and footing reinforcement work ongoing | Nattika Project Dn AE 4 | |
26 Feb 2024 | Bar bending work ongoing | Nattika Project Dn AE 4 | |
25 Feb 2024 | Concrete work and curing ongoing | Nattika Project Dn AE 4 | |
24 Feb 2024 | Concrete work ongoing | Nattika Project Dn AE 4 |