Jal Jeevan Mission (JJM)-Jal jeevan Mission- WSS to Avanur Panchayath in Thrissur District-Construction of 7 LL OHSR- General Civil Work
Project Code
TCRJJM022215661
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
Jal Jeevan Mission
(JJM)-Jal jeevan Mission- WSS to Avanur Panchayath in Thrissur District-Construction of 7 LL OHSR-
General Civil Work
Status
On-going
District
Thrissur
Executing Office
Nattika Project Dn
AS Amount (Rs)
548159000
AS Number
G.O.(Rt)No.134/2022/WRD
TS Amount (Rs)
24400000
TS Number
WRD/KWA-CE(CR)/EST_TS/3334/2022_5_3_2
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
Packages
No.
Project Name
Location
View
1
Jal Jeevan Mission (JJM)-Jal jeevan Mission- WSS to Avanur Panchayath in Thrissur District-Construction of 7 LL OHSR- General Civil Work
Nattika Project Dn
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
03 Jun 2024
7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3.
Nattika Project Dn AE 4
02 Jun 2024
7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3.
Nattika Project Dn AE 4
01 Jun 2024
7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3.
Nattika Project Dn AE 4
30 May 2024
7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3.
Nattika Project Dn AE 4
29 May 2024
7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3.