Jal Jeevan Mission (JJM)-Jal jeevan Mission- WSS to Avanur Panchayath in Thrissur District-Construction of 7 LL OHSR- General Civil Work

Project Jal Jeevan Mission (JJM)-Jal jeevan Mission- WSS to Avanur Panchayath in Thrissur District-Construction of 7 LL OHSR- General Civil Work
Project Code TCRJJM022215661
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission (JJM)-Jal jeevan Mission- WSS to Avanur Panchayath in Thrissur District-Construction of 7 LL OHSR- General Civil Work
Status On-going
District Thrissur
Executing Office Nattika Project Dn
AS Amount (Rs) 548159000
AS Number G.O.(Rt)No.134/2022/WRD
TS Amount (Rs) 24400000
TS Number WRD/KWA-CE(CR)/EST_TS/3334/2022_5_3_2
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 Jal Jeevan Mission (JJM)-Jal jeevan Mission- WSS to Avanur Panchayath in Thrissur District-Construction of 7 LL OHSR- General Civil Work Nattika Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Jun 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3. Nattika Project Dn AE 4
02 Jun 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3. Nattika Project Dn AE 4
01 Jun 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3. Nattika Project Dn AE 4
30 May 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3. Nattika Project Dn AE 4
29 May 2024 7 LL OHSR at AVANUR - Excavation completed.Site levelling done.Drilling& fixing of dowel bars completed. Reinforcement and concreting of levelling course, footing and pedestal completed.Completed soil filling up to plinth level. Reinforcement work for plinth beam completed.Shuttering works for plinth beam concreting completed.plinth beam concreting done..overlapping of main reinforcement bars done to maintain the continuity of the bars throughout the length of the column. 20 mm dia bars are given a lap lenth of 1m and 16 mm dia bars are given a lap length of 80 cm. stirrups are placed in the column.shuttering works for column concreting completed.Concreting of 28 columns are completed.Total quantity of concrete used is 10.896 m3. Reinforcement works for stair case going on.10 mm diameter distribution bars are provided in waist slab.Main bars of 10 mm diameter are given at top and bottom layers of landing slab.Shuttering works for stair case completed. concreting is done for the first flight which consist of waist slab, landing slab and 8 steps (steps are given a rise of 15 cm and tread of 24 cm with M25 concrete Total quantity of concrete used =1.616 m3..shuttering works for second flight of stair completed .reinforcement and shuttering works of first level beams and second flight of stair completed. concreting of 45 beams completed .concreting of landing slab and waist slab of second flight of stair completed.total quantity of concrete used is 23.654 m3. Nattika Project Dn AE 4

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/08/2023
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 23 Feb 2022
TS Date 05 Jul 2023