Overall Project Status

Status Date Overall Project Status Project Officer Contact
17 Sep 2022 Package 1-FHTC Geotagged-2711 nos, FHTC -Total-2717 nos, Package 2 - Pipe laying work progressing. Kollam Project Dn AE
02 Sep 2022 Package 1-FHTC Geotagged-2703 nos, FHTC -Total-2713 nos. total pipe laid - 1750 mtr, Package 2 - Pipe laying work progressing. Kollam Project Dn AE
05 Aug 2022 Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2685 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. Kollam Project Dn AE
02 Aug 2022 Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2685 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. Kollam Project Dn AE
28 Jul 2022 Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2685 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. Kollam Project Dn AE
26 Jul 2022 Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2685 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. Kollam Project Dn AE
25 Jul 2022 Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2681 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. Kollam Project Dn AE
21 Jul 2022 Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2681 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. Kollam Project Dn AE
20 Jul 2022 Package 1-FHTC Geotagged-2681 nos. (today's geo-tagged connections-0-nos) FHTC -Total-2681 nos.( today's physical connections-0 nos.) total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. Kollam Project Dn AE
19 Jul 2022 Package 1-FHTC Geotagged-2681 nos. (today's geo-tagged connections-7-nos) FHTC -Total-2681 nos.( today's physical connections-0 nos.) total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. Kollam Project Dn AE