Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
17 Sep 2022 | Package 1-FHTC Geotagged-2711 nos, FHTC -Total-2717 nos, Package 2 - Pipe laying work progressing. | Kollam Project Dn AE | |
02 Sep 2022 | Package 1-FHTC Geotagged-2703 nos, FHTC -Total-2713 nos. total pipe laid - 1750 mtr, Package 2 - Pipe laying work progressing. | Kollam Project Dn AE | |
05 Aug 2022 | Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2685 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. | Kollam Project Dn AE | |
02 Aug 2022 | Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2685 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. | Kollam Project Dn AE | |
28 Jul 2022 | Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2685 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. | Kollam Project Dn AE | |
26 Jul 2022 | Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2685 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. | Kollam Project Dn AE | |
25 Jul 2022 | Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2681 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. | Kollam Project Dn AE | |
21 Jul 2022 | Package 1-FHTC Geotagged-2681 nos, FHTC -Total-2681 nos. total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. | Kollam Project Dn AE | |
20 Jul 2022 | Package 1-FHTC Geotagged-2681 nos. (today's geo-tagged connections-0-nos) FHTC -Total-2681 nos.( today's physical connections-0 nos.) total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. | Kollam Project Dn AE | |
19 Jul 2022 | Package 1-FHTC Geotagged-2681 nos. (today's geo-tagged connections-7-nos) FHTC -Total-2681 nos.( today's physical connections-0 nos.) total pipe laid - 1750 mtr, Package 2- Didn't start work since no demand get from PWD and KRFB due to monsoon bann. | Kollam Project Dn AE |