| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Dec 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 01 Dec 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 22 Nov 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 13 Nov 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 04 Nov 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 28 Oct 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 22 Oct 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 15 Oct 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. | Thaliparamba WS Section | |
| 03 Oct 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. | Thaliparamba WS Section | |
| 27 Jun 2025 | 1 LL OHSR structure work completed, plasteringcompleted . Connection work completed 926 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work pending | Thaliparamba WS Sub Dn |