Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Dec 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
01 Dec 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
22 Nov 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
13 Nov 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
04 Nov 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
28 Oct 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
22 Oct 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
15 Oct 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Thaliparamba WS Section
03 Oct 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Thaliparamba WS Section
27 Jun 2025 1 LL OHSR structure work completed, plasteringcompleted . Connection work completed 926 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work pending Thaliparamba WS Sub Dn