Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
16 Feb 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
06 Feb 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
28 Jan 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
23 Jan 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
17 Jan 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed Thaliparamba WS Section
12 Jan 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
07 Jan 2026 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
31 Dec 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section
22 Dec 2025 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. Thaliparamba WS Section