| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 21 Feb 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 16 Feb 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 06 Feb 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 28 Jan 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 996 FHTC given .Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 23 Jan 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 17 Jan 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed | Thaliparamba WS Section | |
| 12 Jan 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 07 Jan 2026 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 31 Dec 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section | |
| 22 Dec 2025 | 1 LL OHSR structure work completed, plastering completed . Connection work completed 966 FHTC given out of 996 FHTCs Gravity main nearing to completion. Interconnection Work at Pushpagiri completed. Balance pipe laying for 178m length completed. | Thaliparamba WS Section |