Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
23 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
22 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
20 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
18 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
17 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
15 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
13 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
11 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
09 Feb 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE |