Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
23 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
22 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
20 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
18 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
17 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
15 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
13 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
11 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE
09 Feb 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn AE