Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
06 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
05 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
04 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
03 Jan 2023 | 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V | Kollam Project Dn AE | |
02 Jan 2023 | 7343 FHTCs Completed and 136.188 Km pipe Laying Completed.2127 m GI pipe laid | Kollam Project Dn AE | |
01 Jan 2023 | 7343 FHTCs Completed and 136.188 Km pipe Laying Completed.2127 m GI pipe laid | Kollam Project Dn AE | |
30 Dec 2022 | 7343 FHTCs Completed and 136.188 Km pipe Laying Completed.2127 m GI pipe laid. | Kollam Project Dn EE | |
30 Dec 2022 | 6785 FHTCs Completed and 124.128 Km pipe Laying Completed.90mm(6kg) kochalum moodu thamarakudi laying | Kollam Project Dn AE | |
28 Dec 2022 | 6785 FHTCs Completed and 124.128 Km pipe Laying Completed. Ward 16.fhtc plamoodu progressing | Kollam Project Dn AE | |
27 Dec 2022 | 6785 FHTCs Completed and 124.128 Km pipe Laying Completed.Ward no :9,Pallickal east - House connection work in progress | Kollam Project Dn AE |