Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Mar 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
25 Mar 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
23 Mar 2023 7343 FHTCs ,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
22 Mar 2023 7343 FHTCs ,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
20 Mar 2023 7343 FHTCs ,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
18 Mar 2023 7343 FHTCs 136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
17 Mar 2023 7343 FHTCs 136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
16 Mar 2023 7343 FHTCs 136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn EE
15 Mar 2023 7343 FHTCs 136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn EE
14 Mar 2023 7343 nos FHTCs Completed and 136.188 Km pipe Laying Completed. 2127 m GI completed. Nearly 200 FHTC pending due to the laying pipes by HDD method along MC road pending in KIIFB package V Kollam Project Dn EE