Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Apr 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
10 Apr 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
08 Apr 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
07 Apr 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
05 Apr 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
03 Apr 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
01 Apr 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
31 Mar 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
30 Mar 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE
28 Mar 2023 7343 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 Kollam Project Dn AE